Infraly, LLC - Infraly - London - Carrier Maintenance - April 12th, 2025 – Maintenance details

North America → Phoenix, Arizona experiencing major outage

Infraly - London - Carrier Maintenance - April 12th, 2025

Completed
Scheduled for April 12, 2025 at 7:00 AM – 12:00 PM

Affects

London, United Kingdom Data Center

Under maintenance from 7:00 AM to 12:00 PM

Core Network Infrastructure

Under maintenance from 7:00 AM to 12:00 PM

Hosturly

Under maintenance from 7:00 AM to 12:00 PM

Dedicated Servers

Under maintenance from 7:00 AM to 12:00 PM

Colocation

Under maintenance from 7:00 AM to 12:00 PM

Premium VPS

Under maintenance from 7:00 AM to 12:00 PM

Updates
  • Completed
    April 12, 2025 at 12:00 PM
    Completed
    April 12, 2025 at 12:00 PM
    Maintenance has completed successfully
  • In progress
    April 12, 2025 at 7:00 AM
    In progress
    April 12, 2025 at 7:00 AM
    Maintenance is now in progress
  • Update
    April 11, 2025 at 12:40 PM
    Planned
    April 11, 2025 at 12:40 PM

    The traffic move has been done, and all monitoring is showing positive traffic numbers traversing the network. If you are experiencing any issues, please message support.

  • Update
    April 11, 2025 at 12:30 PM
    Planned
    April 11, 2025 at 12:30 PM

    We are beginning to move traffic to an alternative internet carrier. We will provide updates once done.

  • Update
    April 11, 2025 at 11:53 AM
    Planned
    April 11, 2025 at 11:53 AM

    We have a scheduled timeline for the traffic move to take place. It will begin at 12:30 UTC. Once finished, we will alert via this maintenance post.

  • Update
    April 11, 2025 at 10:59 AM
    Planned
    April 11, 2025 at 10:59 AM

    We anticipate the transfer to happen within the next 3 hours. Please be prepared for a disruption as we move traffic. We will alert via an update before we begin the transition.

  • Update
    April 11, 2025 at 9:45 AM
    Planned
    April 11, 2025 at 9:45 AM

    We are still preparing for the transition to the alternative carrier, which is scheduled to take place today. Once we have a confirmed time, we will update this maintenance post accordingly.

  • Planned
    April 11, 2025 at 5:32 AM
    Planned
    April 11, 2025 at 5:32 AM

    Dear user,

    Please refer to a very important maintenance announcement that may have an impact on hosting services:

    Infraly - London - Carrier Maintenance - April 12th, 2025
    Location Affected: London, UK
    Start Date: April 12th, 2025 @ 8:00 UTC
    Estimated End Date: April 12th, 2025 @ 13:00 UTC

    Summary: One of our primary internet carriers in London will be performing a physical core network relocation within the facility. They have provided us very short notice for this.

    Impact on Customer: All customers in London will experience a brief disruption while we proactively shift traffic to an alternative internet carrier. We are still finalizing the timeline for this turnover and will publish a maintenance notice once the schedule is confirmed. This rerouting will be completed ahead of the provider's maintenance to minimize any impact. We sincerely apologize for the short notice, as we only received this information within the past few hours. We have raised this issue with the internet carrier and made it clear that such limited notice is unacceptable.

    Updates: We will provide updates via our status page throughout the maintenance. You can subscribe for alerts on our status page (https://status.infraly.co).

    If you have any questions, don't hesitate to contact our client relations team via support ticket. Thank you again for your cooperation and support!

    Sincerely,

    Infraly, LLC DBA Hosturly, Physgun, WISP, & Buildurly
    a: 1636 N Cedar Crest Blvd, #122, Allentown, PA 18104, USA
    e: hello@infraly.co
    p: +1 (833) INF-RALY
    w: infraly.co / hosturly.com / physgun.com / wisp.gg / buildurly.com